Essex: Under a third of local road schemes agreed during the last financial year have been completed with only three months of this financial year left to go.

14:17 25 January 2014

Archant

Less than a third of the local road improvement and safety schemes agreed for Essex during the last financial year have been completed with only three months of this financial year left to go.

shares

Figures show that of the 447 Local Highways Panels schemes agreed, funded and signed off in 2012/13 only 29% had actually been delivered by the start of 2014.

The data, obtained from Essex County Council through a Freedom of Information request, also shows that 6% have been cancelled, 59% are expected to be delivered by the end of the 2013/14 financial year and 6% are earmarked for completion some time in 2014/15.

Local Highways Panels have been set up in all 12 districts of the county. The schemes they put forward tend to be local projects aimed at pavement and crossing improvements, new signs, road safety and traffic management.

The figures show that the best-performing districts are Braintree and Maldon, where 44% of schemes in both areas had been delivered by the start of 2014.

The worst is Colchester with a completion rate of just 15% for the 81 schemes put forward.

Critics say Essex County Council, which has responsibilty for carrying out the work, is falling behind in delivering the schemes because of staff cuts.

Others say the authority is doing the best it can in the face of a reduction in funding from central government and a need to focus resources on other highways issues such as repairing potholes.

Green county councillor for Silver End near Witham, James Abbott, who requested the information, said there was an expectation that schemes agreed in one year would be completed in the following 12 months.

“These figures prove what many people involved in this process had suspected – that the delivery performance on the agreed Local Highways Panels schemes is poor to date,” he said.

“We would also question the likelihood of 59% of schemes being delivered in the next few months, as Essex County Council is projecting.

“These are schemes which local communities and parish councils have asked for to make their local roads and paths safer. The cabinet member for highways and colleagues have failed to ensure delivery and have also rejected suggestions as to how to improve the situation – the Greens have suggested using some of the budget to recruit more staff to help clear the backlog.

“The slashing of highways staff at the council over several years means that the council does not have the capacity to get the schemes designed and delivered on time. We don’t blame the officers. We blame the Conservative administration for mismanagement.”

Joint chairman of the Colchester Local Highways Panel, county councillor Anne Brown, admitted there had been a “capacity issue” but that the backlog had to be seen in the light of funding cuts from the coalition Government.

She said: “The county council has been asked to find huge savings and this means it is operating under tremendous restraints. The highways panel in Colchester were very proactive in suggesting projects and we are working through them but it is more realistic that many of them will take two years to complete.

“There has been an enormous problem with potholes and that over-rides everything else.”

An Essex County Council spokesman added: “All 12 Local Highway Panels have been productively recommending schemes for funding allocation which have subsequently been considered and approved by the cabinet member for highways and transportation.

“Due to the high percentage of schemes to be implemented, Essex Highways are continuing to prioritise the delivery of all these highway improvement schemes. Any schemes not yet delivered are currently in the design stage and are all due to be delivered in the next financial year.”

shares

1 comment

  • This sums up this so called government, they can 'talk the talk', but cannot 'walk the walk' !

    Report this comment

    freedomf

    Monday, January 27, 2014

Two teenagers have been arrested following the death of a 14 year old boy after an incident at an address in Thurston.

A peaceful Suffolk village is tonight in shock after the death of a 14-year-old boy from gunshot wounds.

Waveney River Centre.

A seven-year-old girl has died after being pulled unconscious from a swimming pool near Beccles.

The A1092 through Clare is closed due to a road traffic accident.

Police were called at 3.35pm today to attend a serious road traffic collision in Clare.

Knight Owl ridden by George Wood (centre) gets the better of Examiner ridden by Oisin Murphy (right) to win The Suffolk Stakes Race run during QIPCO 2000 Guineas Day of the QIPCO Guineas Festival at Newmarket Racecourse. Julian Herbert/PA Wire

Newmarket celebrated 350 years of world-class horse racing this weekend – and ushered in the anniversary with a Spitfire display.

Entrants set off in last year's Rotary Club of Felixstowe fun run on the resort's seafront.

After a warm and fairly dry weekend, Bank Holiday Monday is set to get off to a dry start in Suffolk but turn wet and blowy by the afternoon.

More than 600 vehicles - cars, buses, military vehicles and motorcycles - taking part in the 46th annual Ipswich to Felixstowe Historic Vehicle Run. Christchurch Park. Left to right, Ross and Stuart Holman.

Hundreds of car owners took advantage of one of the first good days of the year to take part in Sunday’s historic vehicle run from Ipswich to Felixstowe.

Norfolk Police. Photo: Steve Adams

Police were called to the scene of a three car crash on the A146, near the Morrisons roundabout, at around 11.24am.

Most read

Great Days Out

cover

Click here to view
the Great Days Out
supplement

View
HOT JOBS

Show Job Lists

Streetlife

Newsletter Sign Up

Great British Life

Great British Life
MyDate24 MyPhotos24