Ipswich: Frustration over lack of Waterfront progress

17:01 08 February 2013

Ipswich Waterfront.

Ipswich Waterfront.

Archant

Frustration is growing in the town over the lack of development work at The Mill and Regatta Quay on the Waterfront.

shares

Timeline

2006: Demolition work takes place at two of the largest Waterfront plants – Pauls Maltings and Cranfields Mill – which are to become Regatta Quay and The Mill respectively.

2007: Work starts on both sites, the first of two towers at Regatta Quay is “topped out”.

2009: Work on the Regatta Quay halts with the skeleton of the second tower left incomplete.

Jan 2010: Regatta Quay developer City Living goes into administration after talks with its banker Anglo Irish. Grant Thornton appointed administrators.

May 2010: The Mill developer Wharfside Regeneration is put into administration by its bank Allied Irish. Baker Tilly appointed administrators.

Late 2010: Irish banking crisis. Toxic elements of major banks – including those to the two Ipswich developments – transferred to new body the National Asset Management Authority (NAMA).

November 2011: Officials from NAMA visit Ipswich Waterfront. As they now control both sites they decide to put them under a single administrator, Baker Tilly. They also reveal a masterplan will be drawn up during the spring of 2012 aimed at finding a way to restart work.

March 2012: Hopes rise that work on The Mill could soon resume. About two thirds of the flats remain unfinished.

February 2013: Still waiting for substantial work to resume on the project, officials speak of their frustration at the lack of progress.

The two developments were combined into a single unit 15 months ago – and at that time there were promises that a masterplan for work to resume would be drawn up within months.

However since then little has happened at the site – which includes the notorious “wine rack” skeleton of the second Regatta Quay tower and The Mill tower, the tallest building in Suffolk.

The site is controlled by Ireland’s National Asset Management Agency (NAMA) – the body set up to take on the “toxic debts” of Irish banks which failed in the financial crisis.

Ipswich MP Ben Gummer brought officials from NAMA to Ipswich in November 2011. After seeing the sites they agreed to combine the two sites under a single joint administrator, Baker Tilly.

At the time Mr Gummer was told that the masterplan would be drawn up within months and that should allow work to restart.

However there has been no substantial new work on the site – although some flats that were nearing completion at the time building work stopped in 2009 have been finished and sold.

Now Mr Gummer is getting fed up with the delay.

He said: “I am getting increasingly frustrated with the rate of progress with the Wine Rack. The new administrators have now been in place for over a year and we have still not seen much of what I have been promised.

“The wine rack is a blight on the town and needs to be dealt with rapidly if redevelopment is to take place. I am sure that Baker Tilly and NAMA have the right intentions but they now need to show some real action.”

Ipswich council chief executive Russell Williams said many at the authority shared Mr Gummer’s frustration, but he was aware that the administrator and its agent, Savills, were trying to move the development along.

He said that the experience of major dockside redevelopments in other towns and cities had been that they often got caught in recessions – leading to work being suspended for some time before they were finished.

Andy Redman from Savills said there was a great deal going on behind the scenes which should allow work to restart in the not-to-distant future, but he accepted things had moved more slowly than was hoped.

He said: “I can understand the frustration, but it has taken longer than we expected to establish who owns all the flats and to complete all the legal processes.

“We are there now and hope to have a plan to restart the work before too long.”

Mr Redman said the first work was likely to be the completion of The Mill tower before attention turned to the “wine rack.”

Nobody from Baker Tilly was available for comment.

shares

2 comments

  • Is it any wonder no developer wants to take this project on when we have our own mp slating the building ! our town center is slowly dying due very poor planning over the last 30 years there is still no link between the waterfront and the town center we also have people trying to stop the snoasis project a scheme which if it does go ahead would bring jobs and tourism to the town although think people there may just go to Bury as their town centre is much more attractive !

    Report this comment

    penfold the mole

    Friday, February 8, 2013

  • Does anybody really believe that if the so-called "wine rack" ever gets finished it'll look any better than it does now? On the evidence of everything else that's been built round the Wet Dock, it's highly unlikely.

    Report this comment

    beerlover

    Friday, February 8, 2013

The views expressed in the above comments do not necessarily reflect the views of this site

Lord Deben John Gummer, Christine Block, from Deben Estuary Partnership, Karen Thomas, from Water Management Alliance, Graham Henderson, from DEP, Simon Amstutz, from AONB, Therese Coffey MP, David Kemp from the Environment Agency, and Suffolk Coastal District Councillor Andy Smith gathered to launch the Deben Estuary Plan.

Three years of work have created a new community-led blueprint to protect and manage one of Suffolk’s treasures, the River Deben estuary

Detectives investigating a burglary at a home in Colchester have issued an efit of a man they would like to identify in connection with the incident.

Age UK is looking for volunteers to take part in a video

Bosses at Age UK Suffolk are looking for 10 older people to take part in a new promotional video that is being made to show off the work of the charity.

An Abellio Greater Anglia train at Colchester

Rail delays at Colchester have been caused by a broken down train.

Rendlesham Care Centre rated ‘good’ by CQC (L-R) Danielle Brown, Administrator; Liz Slight, Home Manager; Maxine Crisp, Carer; Fabian Lossa, Carer; Rachael Last, Receptionist

Rendlesham Care Centre was found to provide a safe, effective, caring, responsive and well-led service according to the CQC report.

A diversion has been put in place

Severe traffic delays in Chelmsford have been caused by a traffic collision.

Woodbridge Carnival fireworks 2015.

People in an east Suffolk town are being asked to vote with their cash if they want a fireworks display next year.

Station Hill in Bury St Edmunds, which is being redeveloped.

Plans for more than 100 flats near the train station in Bury St Edmunds - an area of the town that is earmarked for regeneration - have been recommended to be refused.

Suffolk Coastal MP Dr Therese Coffey (centre) with members of her team and Fern Howard (left) from the Alzheimer’s Society

It follows a visit by the Alzheimer’s Society, who run the Dementia Friends scheme, to help Dr Coffey and her staff understand the effect of dementia on everyday lives.

Lifeboat

Coastguard services were called to rescue a teenager in Corton, near Lowestoft yesterday evening.

Most read

Most commented

Topic pages