Sizewell C: Construction of any new nuclear plant unlikely before 2018 - at least two years later than expected

12:05 03 February 2014

The proposed project to build Sizewell C

The proposed project to build Sizewell C


Construction of Sizewell C is unlikely to begin before 2018, according to a senior Suffolk planner - at least two years later than widely expected. Electricity would start to be generated 10 years later, in 2028.


EDF Energy has consistently declined to set out its target schedule for getting the proposed nuclear power station through the planning process.

However, Philip Ridley, head of planning at Suffolk Coastal District Council, believes the earliest that building of the twin European Pressurised Reactors (EPRs) can start is 2018.

The power station - costing an estimated £14billion - is scheduled to generate 3,200 megawatts of power, enough to meet demand from five million homes.

In making his assessment – reported to members of the local authority’s Sizewell C task group – Mr Ridley said he had taken into account experience at Hinkley Point in Somerset where the first of the UK’s new generation of nuclear power stations is due to be built.

He told the EADT that subject to a range of public consultation and planning process factors the start date for Sizewell C could be 2018 at the earliest but that there were also “financial hurdles” for the project to overcome.

Delay in agreeing financial arrangements for Hinkley has inevitably led to a slow-down in the progress of the Suffolk project, which at one time looked set for site works to commence in 2016.

The European Commission is still examining whether the financial deal for Hinkley meets “state aid” regulations and there is a possibility it could launch a full investigation, a move which could cause a further 18-month delay.

Government ministers were hoping that both Hinkley Point C and Sizewell C would be up and running by 2025 to help plug an emerging gap in energy supply.

Even if construction starts in 2018, Sizewell C would not be generating electricity before 2028.

However, problems causing construction delays, as well as price hikes, have been experienced in Finland and France where similar EPRs are being built.

Plans for a third nuclear power station on the Suffolk coast were first mooted 30 years ago.

Detailed proposals were finally published in 2012 and the first stage of the public consultation exercise was launched in November of that year.

Bosses predict the project will generate £100 million a year during construction and £40m a year thereafter for the local economy, with a workforce of around 5,600 at the peak of construction and 900 permanent jobs once the power station is built.

Full details of the result of the 11-week consultation are still to be published and a second phase is now unlikely to be launched until the autumn of this year.

With the stage two consultation and assessment likely to occupy a further 12 months it is likely to be late in 2015 before a formal planning application can be submitted to the Planning Inspectorate which will then have nine months to carry out an examination and make a recommendation to Energy Secretary, Ed Davey.

EDF Energy has confirmed that stage two of the Sizewell C public consultation will start “later this year”.

A spokeswoman said: “The timetable beyond that will be influenced by the issues and suggestions raised in the responses we receive at Stage 2, which we will need to carefully consider and factor into our proposals.

“It is also important to note that the Sizewell C project has always been conditional upon progress to a final investment decision for Hinkley Point C in Somerset, which we also hope to announce this year.”

A planning application for Sizewell B was submitted in 1981 but it was not until 1987 that construction work began.

Most of the delay was down to a 27-month long public inquiry and the inspector, Sir Frank Layfield QC, took a further two years to draw up his report.

The public inquiry system for major infrastructure projects has since been scrapped in a bid to speed up the process for getting a decision.


1 comment

  • The Chinese are building 2 EPR's at Taishan, starting in 2009. They will be complete this year. 5 years in China and 10 years in the UK. Why?

    Report this comment

    Stephen Kennedy

    Monday, February 3, 2014

Police closed Felixstowe Road, Ipswich.

A man has been taken to hospital after the motorcycle he was riding collided with a van.

Suffolk Fire and Rescue Service called to Foxhall Road, Ipswich.

Firefighters were called to help a young child who got their head trapped between two bollards.

Travellers in Jaywick.

A group of travellers today returned to a site they had previously camped on in Jaywick - but were stopped in their tracks.

The large scale police operation in Potash Road, Wyverstone.

A village stalwart and chairman of a Suffolk parish council hid hundreds of illegal guns in a secret room at his house, a court heard.

The ice skating rink currently being installed in the Arc shopping centre in Bury St Edmunds

Limited parking capacity in Bury St Edmunds is set to be boosted by 420 extra spaces over the festive period after local brewer Greene King offered free use of its staff car park at weekends.

Kujtin Rexha was jailed for 11 years at Chelmsford Crown Court

Braintree man Kujtin Rexha has been jailed for 11 years for rape and holding a 17-year-old girl against her will for two and a half months.

James McAtear, headteacher of Hartismere School

A top headteacher has attacked Suffolk County Council and the Schools Adjudicator.

Most read

Most commented

Topic pages

Local business directory

Our trusted business finder

Property search

e.g. Oxford or NW3
Powered by Zoopla

Digital Edition

Read the East Anglian Daily Times e-edition today E-edition

Great British Life

Great British Life
MyDate24 MyPhotos24