Mathew McBride, North Star’s head of programme management, outlines the planning behind safe, efficient and cost-effective dry docks.

Every two and half years, each of our ships docks for the equivalent of a car’s MOT, involving extensive inspections, repairs and certification renewals to ensure they remain safe and fit for service.

When a dry docking goes well, most clients never notice it happened, yet it’s one of the most important events in a ship’s life. It involves taking a vessel out of the water to inspect, maintain and repair systems that cannot be accessed at sea.

This also covers activities from accommodation-related repairs to replacing a galley if required – all with the crews still living onboard during the process.

We have two fleets: service operations vessels (SOVs) and associated daughter craft for the offshore wind sector, and emergency response and rescue ships (ERRVs) servicing our conventional energy clients’ installations.

To give an indication of the logistics involved, this means that we’ll complete 20 to 21 dry dockings next year, each turned around in one to three weeks. The most important part of a dry dock is the specification, and if it’s done right, time in the yard is the easy part.

Ideally, planning starts a year out: agreeing overhaul requirements with equipment manufacturers, identifying obsolete systems and ordering long-lead parts, some of which carry six-month lead times. We work to a five-year plan showing when vessels are due for docking and what requires replacement.

Mathew McBride, head of programme management at North Star (Image: North Star)

The Grampian Don, one of our 36-strong ERRV fleet, shows what this preparation delivers. This was one of the first dockings led by our new dry dock engineering team, which we were ready well ahead of her arrival at MacDuff Shipyards in Fraserburgh.

Our operations and projects teams agreed the scope with her crew and the manufacturers, starting with what was and wasn’t working. I was aboard several times and saw the crew taking real pride in her condition. She left the dock safely, on budget and on time for sea trials.

Safety, time and budget are three tests of a good dry dock. The fourth is whether the crew are happy, because I see the vessel and its crew as my client.

With our SOV fleet growing, next year’s programme is larger than usual, bringing engines, thrusters and gearboxes back in line with manufacturer specifications. The process hasn’t changed much in 15 years, but success still depends on early preparation.

The Grampian Don’s captain, Chris Jeffrey, has worked on the ERRV since it joined the North Star fleet.

“We work with dry docks along the UK’s east coast, and the best partners combine a skilled workforce with competence and transparency – honesty from a yard goes a long way,” he said.

“I’ve seen the Don through a total of five dry docks now, and this recent one in Fraserburgh went really well. The dock’s yard staff were excellent throughout, ensuring we remained on time and on budget."

For more information, visit north-star.co.uk

This story is also published in Insight Energy magazine, covering the latest news from the UK's energy sector. Read the latest edition here.